Desalination Plant Dispute Escalates in Mazotos as New Protest Planned

Header Image

Protesters to demand cancellation of the desalination project and reject any compensatory measures offered in return

 

Construction of the mobile desalination plant in the coastal area of Mazotos will proceed as planned, despite opposition from a section of local residents.

Speaking to Politis radio, Water Development Department Director Iliana Tofa Christidou made clear that all necessary approvals for the project have been secured. She said the design had been adjusted to address environmental concerns raised by the local authority and residents.

According to her, consultations were held before the construction phase began, including meetings at various levels and two community-wide gatherings during which details of the project and its environmental aspects were presented.

She added that one of the most significant changes made to the project's design concerns the disposal of brine into the sea. The plan now provides for the brine to be discharged at a greater depth and further from the shoreline through a specialised dispersion system.

Regarding the compensatory measures sought by Mazotos, Ms Tofa said the matter is under consideration at the political level, with the involvement of the relevant ministries and government departments.

She also noted that the Mazotos desalination plant will be a mobile facility and is expected to operate for up to seven years. Financing, operation and eventual dismantling of the unit will be the responsibility of the contractor, while the state will purchase the water produced.

She further stated that the necessary environmental studies have been completed and the relevant permits obtained, including authorisation for the removal of trees obstructing access to the site.

She stressed, however, that plans provide for tree planting around the installation and restoration of the area afterwards.

The Water Development Department director said water produced by the Mazotos plant would be directed primarily to Larnaca district. Any surplus quantities would also help strengthen water supplies to Nicosia and Famagusta.

New protest planned

Meanwhile, a new protest against the desalination plant has been scheduled for 11 a.m. on Sunday, 22 November, in the area known as "Petountas", organisers announced.

The demonstration is being organised by members of the Initiative Group for the Preservation of the Mazotos Coast.

Protesters will call for the decision to build the desalination plant to be revoked and will make clear that they will not accept any compensatory measures in exchange.