Limassol Residents Complain of Night-Time Construction Work as Site Hours Remain Unregulated

Header Image

With no legal limit on site hours, the authorities pass responsibility on, while residents report noise on Sundays and holidays.

Thousands of our fellow citizens who live near large building sites are complaining bitterly, as site operating hours are completely unregulated, causing multiple problems. The issue is most acute in Limassol. Because of extensive construction and the building of huge structures such as towers, residents in some neighbourhoods say they have not slept peacefully for months.

Residents told Politis that at some building sites concrete mixers are emptied at 2am or 3am. In another case, at a site near the city centre, workers were cutting steel at 4:30am. Incidents have been recorded on video in the possession of Politis.

A legal gap

The main cause of the problem is a serious legal gap. No regulation sets the hours a building site may operate, even in a residential area where heavy outdoor work is carried out. The only rules relate mainly to working hours in the construction industry, as set out in the collective agreement. In a number of cases, however, especially recently, subcontractor crews are employed outside the framework of the collective agreement.

Authorities pass the issue around

The responsible authorities are passing the ball from one to another. The Department of Labour Inspection says it is not responsible for working hours and refers nuisance complaints to municipalities and the police. The police refer complaints back to the Department of Labour Inspection, which checks safety at building sites. Municipalities throw up their hands, as they consider it very difficult, or in practice impossible, to check building sites under the nuisance provisions. One difficulty is carrying out noise measurements in time, when such a measurement is needed to prove an offence and issue an out-of-court fine.

There are also complaints of undeclared or other illegal work at building sites. The lack of rules on hours appears to suit those who use such practices, as on-site checks are extremely difficult at night. At sites employing mainly foreign workers, often outside the collective agreement, the usual practice of stopping work on Sundays and public holidayshas also slipped. For many residents, the noise continues on days of rest as well.

Some work can, as an exception, reasonably start very early. In concrete pouring, for example, especially in summer, starting before temperatures rise helps control the temperature of the concrete. On large projects, continuous concrete pouring can last many hours and must be completed without interruption. The earlier it starts, the more trips the concrete mixers can make. As a result, a large "operation" is often set up that can last almost 24 hours.

Unauthorised road closures

There are also complaints of unauthorised road closures to make work easier. Sometimes a road is closed without a permit. In other cases, subcontractors carrying out different work submit successive requests, without it being apparent that they concern the same location and the same building site. As a result, each request may be examined separately, even though for residents these are successive closures of the same road. On large and complex projects, this practice is tending to become the rule.

Under current law, the practical way for residents to act on noise is to file a complaint under the general provisions on nuisance and public peace. In theory, a building site could operate in shifts, even around the clock, as long as it does not cause a nuisance and complies with its permit conditions and labour legislation.